Installer Technical Briefing
DC Solar
Direct to Battery

Apache Junction, AZ — Off-grid recharge for existing Anker Solix F3800 system. Not grid tied. No interconnection.

4,250W New Solar
10 Panels
21kWh Battery Bank
Section 01

Do Not Touch

This site has an existing solar and battery system. The work is additive only. Three things are off limits — no exceptions.

Leave These Alone
Enphase System 24-panel SolarWorld 295W array with IQ7 microinverters. Grid tied. Currently net metering with SRP. Do not disconnect, rewire, or touch the combiner box, the IQ Gateway, or any panel connection.
HPP Unit Anker Solix Home Power Panel on the wall. The interconnection, the transfer switch logic, and the existing F3800 power station connections are already configured and working. Do not open it, rewire it, or change any settings.
SRP Meter / Interconnect The outdoor SRP net meter and existing PV disconnect are tied to the Enphase system under an active interconnection agreement. Do not touch anything on the utility side of the meter.
Why: The existing Enphase system handles daily production and net metering. The HPP handles whole-home backup. Both are working correctly. This project adds solar charging to the batteries — it does not modify what already works.
Section 02

Why DC Direct

Several approaches were evaluated. DC direct into the F3800 input ports is the correct solution for this specific system.

Why not microinverters + grid tie?

The customer's IQ7s are grid-following — they shut off when grid drops. Adding IQ8s or APsystems micros would produce AC that goes to the grid, not the batteries. During an outage — the exact moment she needs recharge — AC-coupled solar stops working due to anti-islanding. Her batteries drain with no replenishment.

Why not a hybrid inverter?

A hybrid inverter to handle both the existing Enphase AC output and a new DC string would require AC coupling capacity for 11kW+ of combined solar, a battery inverter, and significant rewiring. Cost climbs past $5,000 in hardware alone before touching the existing system.

Why DC direct works here

The F3800 Plus has dual MPPT inputs rated 11–165V, 13.9A max. The original F3800 has dual inputs rated 11–60V, 27A max. The Trina 425W panels string perfectly within these limits. DC flows directly from panels into batteries — no inverter, no grid connection, no anti-islanding problem. Solar charges the batteries whether the grid is up or down.

What this doesn't do

These 10 panels do not export to the grid. They do not show in the Enphase app. They do not interact with SRP's net metering. They charge the F3800s. That is their only job.

Section 03

String Configuration

Ten panels across four strings — two per F3800 unit. String config is dictated by each unit's voltage and current limits. Do not deviate from this layout.

F3800 Plus 165V Max · 13.9A Max
Port 1
P1
P2
P3
150.6V Voc · 10.61A Isc
Port 2
P4
P5
P6
150.6V Voc · 10.61A Isc
Config: 3S per port Connector: MC4 → XT60 Headroom: 14.4V
Original F3800 60V Max · 27A Max
Port 1
P7
P8
50.2V Voc · 21.22A Isc
Port 2
P9
P10
50.2V Voc · 21.22A Isc
Config: 2P per port Connector: MC4 branch → XT60 Headroom: 9.8V
Critical Voltage Warning
Original F3800 Max input is 60V. A single Trina 425W panel is 50.2V Voc — already using 84% of the limit. Do NOT wire panels in series on this unit. Parallel only. Two panels in series = 100.4V = destroyed unit.
Section 04

Rapid Shutdown System

NEC 690.12 / NEC 2023 compliant. Module-level shutdown via PLC signal. All 10 panels covered by one transmitter.

APsystems 408006 Transmitter — 1 unit
IP65 outdoor enclosure. Single core handles all 4 strings up to 30 modules. Power from F3800 AC output circuit — must be on same circuit for NEC compliance. Loop all DC positive conductors through the core. When AC power is cut, all RSD devices shut down within seconds.
●●
APsystems RSD-D Duo PLC — 4 units
Each unit covers 2 panels. Clip to panel frame. 4 units × 2 panels = 8 panels covered. Used on all parallel-configured ports (original F3800) and the first two panels of each F3800 Plus series string.
APsystems RSD-S Single PLC — 2 units
Each unit covers 1 panel. One per F3800 Plus string — handles the 3rd panel in each 3S series string. Must be PLC version to communicate with the 408006 transmitter.
Verify on arrival: All RSD devices must be PLC version — not the older wireless version. The 408006 transmitter communicates via power line communication through the DC wire, not RF.
Section 05

Equipment Specs

Key specs and datasheet links for every component on this job.

Trina Solar Vertex S 425W 10 panels
Pmax425W
Voc50.2V
Vmp42.2V
Isc10.61A
Imp10.08A
Dimensions1762×1134×30mm
Frame30mm anodized Al
Max Series Fuse20A
PowerField PowerRack 1200 12 buckets
Module Width1120–1150mm
Trina Width1134mm ✓
Layout2 rows × 5 panels
Buckets/Row6 (shared)
BallastCustomer provides
Made inUSA
APsystems RSD-D Duo PLC 4 units
Panels/Unit2
Max Voltage1500V UL
SignalPLC (power line)
NEC690.12 2017/20/23
EnclosureIP68 / NEMA 6P
Min Op Voltage8V
APsystems RSD-S Single PLC 2 units
Panels/Unit1
SignalPLC (must match)
NEC690.12 compliant
PlacementF3800 Plus Port 1 P3, Port 2 P6
APsystems 408006 Transmitter Kit 1 unit
CoreSingle core
Max Modules30
Max Current/Core160A
Power Supply85–264VAC
EnclosureIP65 outdoor
StandardSunSpec certified
Anker Solix F3800 Plus 1 unit — existing
Capacity3,840Wh LFP
AC Output6,000W
Solar Ports2× MC4
MPPT Range11–165V
Max Isc/Port13.9A
Max Solar In3,200W total
Anker Solix F3800 (Original) 1 unit — existing
Capacity3,840Wh LFP
AC Output6,000W
Solar Ports2× XT60
Voltage Range11–60V ⚠️
Max Current27A per port
Max Solar In2,400W total
Section 06

Disconnects & Wire Run

DC Disconnects 2× DC rated
Placement One per F3800 unit at array boundary
Why 2 not 4 Unit-level isolation sufficient for this system
Wire gauge 10 AWG PV (USE-2)
Run distance ~10 feet
Conduit Customer pre-laid Schedule 40 PVC
Burial depth 18" minimum
Installer task Pull wire only — trench done by customer
Location: Ground mount is adjacent to the connex on the property — approximately 10 feet from the F3800 units inside. Voltage drop at this distance on 10 AWG is negligible.
Section 07

Scope Split

What you're doing. What she's already done or handles herself.

Your Scope
Mount 10 panels on PowerRack 1200 buckets
Install RSD-D Duo and RSD-S devices at each panel
Mount and wire 408006 transmitter outdoor kit
Pull DC wire through pre-laid conduit
Install 2× DC disconnects
Terminate all strings into F3800 XT60 / MC4 ports per string config
Commission and test — verify charging on both units
Customer Scope
Trenching
Conduit lay and glue
All materials ordered and on site
Ballast for PowerRack buckets
Existing system — fully her responsibility
Final Reminder
This job Is a DC only install. No AC inverter. No grid connection. No utility notification. No interconnection paperwork. If something doesn't look right on site, stop and call before proceeding.